[FIXED] Critical Path Method Algorithm

 September 06, 2022     algorithm, java   

Issue

Where can I find a Java implementation of the Critical Path Method Algorithm? I am sure there's some implementation in the cloud. I have already searched on google obviously, but haven't found any implementation that works well. That's why I am asking.

Thanks in advance.


Solution

Here is an implementation of the algorithm based on the explanation provided on this page There is a wrapper class to hold the task, cost, and critical path cost. It starts by calculating the critical cost as the maximum critical cost of all dependencies plus its own cost. Then once the critical costs are available it uses a comparator to sort the tasks based on the critical cost with dependency as a tie breaker (choosing randomly if there is no dependency). Note that an exception will be thrown if there is a cycle and it will fail if any of the costs are negative.

Here is the implementation:

public class CriticalPath {

  public static void main(String[] args) {
    //The example dependency graph from
    //http://www.ctl.ua.edu/math103/scheduling/scheduling_algorithms.htm
    HashSet<Task> allTasks = new HashSet<Task>();
    Task end = new Task("End", 0);
    Task F = new Task("F", 2, end);
    Task A = new Task("A", 3, end);
    Task X = new Task("X", 4, F, A);
    Task Q = new Task("Q", 2, A, X);
    Task start = new Task("Start", 0, Q);
    allTasks.add(end);
    allTasks.add(F);
    allTasks.add(A);
    allTasks.add(X);
    allTasks.add(Q);
    allTasks.add(start);
    System.out.println("Critical Path: "+Arrays.toString(criticalPath(allTasks)));
  }

  //A wrapper class to hold the tasks during the calculation
  public static class Task{
    //the actual cost of the task
    public int cost;
    //the cost of the task along the critical path
    public int criticalCost;
    //a name for the task for printing
    public String name;
    //the tasks on which this task is dependant
    public HashSet<Task> dependencies = new HashSet<Task>();
    public Task(String name, int cost, Task... dependencies) {
      this.name = name;
      this.cost = cost;
      for(Task t : dependencies){
        this.dependencies.add(t);
      }
    }
    @Override
    public String toString() {
      return name+": "+criticalCost;
    }
    public boolean isDependent(Task t){
      //is t a direct dependency?
      if(dependencies.contains(t)){
        return true;
      }
      //is t an indirect dependency
      for(Task dep : dependencies){
        if(dep.isDependent(t)){
          return true;
        }
      }
      return false;
    }
  }

  public static Task[] criticalPath(Set<Task> tasks){
    //tasks whose critical cost has been calculated
    HashSet<Task> completed = new HashSet<Task>();
    //tasks whose ciritcal cost needs to be calculated
    HashSet<Task> remaining = new HashSet<Task>(tasks);

    //Backflow algorithm
    //while there are tasks whose critical cost isn't calculated.
    while(!remaining.isEmpty()){
      boolean progress = false;

      //find a new task to calculate
      for(Iterator<Task> it = remaining.iterator();it.hasNext();){
        Task task = it.next();
        if(completed.containsAll(task.dependencies)){
          //all dependencies calculated, critical cost is max dependency
          //critical cost, plus our cost
          int critical = 0;
          for(Task t : task.dependencies){
            if(t.criticalCost > critical){
              critical = t.criticalCost;
            }
          }
          task.criticalCost = critical+task.cost;
          //set task as calculated an remove
          completed.add(task);
          it.remove();
          //note we are making progress
          progress = true;
        }
      }
      //If we haven't made any progress then a cycle must exist in
      //the graph and we wont be able to calculate the critical path
      if(!progress) throw new RuntimeException("Cyclic dependency, algorithm stopped!");
    }

    //get the tasks
    Task[] ret = completed.toArray(new Task[0]);
    //create a priority list
    Arrays.sort(ret, new Comparator<Task>() {

      @Override
      public int compare(Task o1, Task o2) {
        //sort by cost
        int i= o2.criticalCost-o1.criticalCost;
        if(i != 0)return i;

        //using dependency as a tie breaker
        //note if a is dependent on b then
        //critical cost a must be >= critical cost of b
        if(o1.isDependent(o2))return -1;
        if(o2.isDependent(o1))return 1;
        return 0;
      }
    });

    return ret;
  }
}


Answered By - M. Jessup
Answer Checked By - Mildred Charles (JavaFixing Admin)
  • Share This:  
  •  Facebook
  •  Twitter
  •  Google+
  •  Stumble
  •  Digg
This Answer collected from stackoverflow and tested by JavaFixing community admins, is licensed under cc by-sa 2.5 , cc by-sa 3.0 and cc by-sa 4.0
Newer Post Older Post Home

Popular Posts

  • [FIXED] How to make a smooth time-based animation with JavaFx AnimationTimer?
    Issue I'm making a very simple animation using JavaFX. My goal here is just to have a ...
  • [FIXED] Maven 3.1.0 update central repository to https
    Issue I'm using maven 3.1.0 in command line mode to upload jar files to my local maven...
  • [FIXED] org.springframework.beans.factory.UnsatisfiedDependencyException: Error creating bean with name 'messageSender'
    Issue Error while trying to publish a message from spring boot to Google cloud platform pu...
  • [FIXED] How to create spring-based executable jar with maven?
    Issue I have a Maven based Spring-WS client project that I want to package as a single jar...
  • [FIXED] JPA @OrderBy with Hibernate
    Issue Im using hibernate and want to use @OrderBy to order a resultSet : public class To...
  • [FIXED] Spring @RequestParam custom type conversion
    Issue How do I create a custom type converter for a boolean parameter in a GET request? F...
  • [FIXED] Jenkins Remove Item via curl with api
    Issue I am somewhat new to using API's. In the below question, the answer mentions usi...
  • [FIXED] Elasticsearch stops working after I run the springboot Java program and elasticsearch transport node is not loading in my Java Program
    Issue Elasticsearch version 8.1.3 Java version 1.8 Im trying to connect elasticsearch wit...
  • [FIXED] 'gradlew' is not recognized as an internal or external command error in Android Studio terminal
    Issue Getting error - 'gradlew' is not recognized as an internal or external comma...
  • [FIXED] Hibernate table not mapped error in HQL query
    Issue I have a web application that use Hibernate to make CRUD operations over a database....

Labels

.class-file .cod-file .net .net-6.0 .net-core .net-maui .netrc .obj 12factor 2d 2d-games 3-tier 32bit-64bit 3d 3g 404-page 64-bit a-star aapt aapt2 aar ab-testing abap abap-adt abbreviation absolute-path absolutelayout abstract abstract-class abstract-data-type abstract-methods abstract-syntax-tree abstraction acceleo accent-color access-log access-modifiers access-specifier access-token accessibility accessibilityservice accessible accordion account accountmanager achartengine acl acr action actionbarsherlock actioncontext actionevent actionlistener actionresult actionscript-2 actionscript-3 active-directory active-window activemq activemq-artemis activiti activity-lifecycle activitynotfoundexception actuator ada adapter adaptive-cards adb adbwireless add addition adfs adjacency-matrix administrator admob adobe adoptopenjdk ads adsense adt aem aem-6 aerospike aerospike-loader aes aes-gcm aether agent aggregate aggregate-functions aggregation aggregation-framework agora.io aidl airflow airflow-api airflow-scheduler aix ajax ajaxform ajdt ajp akka akka-http alarmmanager alert alexa-skills-kit alfresco alfresco-maven algebraic-data-types algorithm alignment allegro allegro5 allocation allure alpha alpine alpine-linux alpn alsa altbeacon amadeus amazon-ami amazon-appstore amazon-athena amazon-aurora amazon-cloudwatch amazon-cognito amazon-dynamodb amazon-dynamodb-local amazon-ec2 amazon-ecr amazon-ecr-public amazon-ecs amazon-efs amazon-eks amazon-elastic-beanstalk amazon-elb amazon-emr amazon-iam amazon-kinesis amazon-kinesis-video-streams amazon-linux amazon-mq amazon-neptune amazon-rds amazon-redshift amazon-s3 amazon-ses amazon-sns amazon-sqs amazon-vpc amazon-web-services ambari ambiguous amd amqp anaconda anagram anchor andengine andengine-gles-2 android android-10.0 android-11 android-12 android-13 android-2.2-froyo android-4.2-jelly-bean android-4.4-kitkat android-5.0-lollipop android-6.0-marshmallow android-7.0-nougat android-7.1-nougat android-8.0-oreo android-9.0-pie android-aab android-actionbar android-actionbar-compat android-activity android-adapter android-adapterview android-alertdialog android-animation android-anr-dialog android-api-30 android-api-31 android-api-levels android-app-bundle android-app-links android-app-signing android-appbarlayout android-appcompat android-application-class android-appwidget android-architecture android-architecture-components android-architecture-navigation android-arrayadapter android-assets android-asynclistdiffer android-asynctask android-audiomanager android-authenticator android-auto android-automotive android-background android-billing android-bitmap android-ble android-bluetooth android-bottomappbar android-bottomnav android-bottomnavigationview android-bottomsheetdialog android-broadcast android-browser android-build android-build-flavors android-bundle android-button android-c2dm android-camera android-camera-intent android-camera2 android-camerax android-canvas android-cardview android-checkbox android-chips android-collapsingtoolbarlayout android-color android-compose-button android-compose-image android-compose-textfield android-concatadapter android-configchanges android-connectivitymanager android-constraintlayout android-contacts android-contentprovider android-contentresolver android-context android-contextmenu android-coordinatorlayout android-cursor android-cursorloader android-custom-view android-customtabs android-dark-theme android-darkmode android-database android-databinding android-date android-datepicker android-debug android-deep-link android-design-library android-developer-api android-device-controls android-device-monitor android-dialer android-dialog android-dialogfragment android-diffutils android-displaymanager android-download-manager android-doze android-drawable android-edittext android-emulator android-espresso android-external-storage android-facebook android-ffmpeg android-file android-fileprovider android-filterable android-flavordimension android-fonts android-fragmentactivity android-fragments android-framelayout android-fullscreen android-gallery android-geofence android-glide android-go android-googleapiclient android-gps android-gradle-7.0 android-gradle-plugin android-graphics android-gravity android-gridlayout android-handlerthread android-image android-imagebutton android-imageview android-implicit-intent android-inflate android-input-method android-install-apk android-instant-apps android-instrumentation android-intent android-intent-chooser android-internal-storage android-jetifier android-jetpack android-jetpack-compose android-jetpack-compose-button android-jetpack-compose-canvas android-jetpack-compose-layout android-jetpack-compose-list android-jetpack-compose-material3 android-jetpack-compose-pager android-jetpack-compose-path android-jetpack-compose-scaffold android-jetpack-compose-testing android-jetpack-compose-text android-jetpack-datastore android-jetpack-navigation android-jobscheduler android-json android-junit android-keypad android-keystore android-koin android-ksoap2 android-ktx android-launcher android-layout android-layout-weight android-library android-lifecycle android-linearlayout android-listadapter android-listfragment android-listview android-livedata android-loader android-loadermanager android-location android-logcat android-looper android-managed-profile android-management-api android-manifest android-mapview android-maven-plugin android-mediacodec android-mediaplayer android-mediasession android-menu android-messaging android-motionlayout android-multidex android-music-player android-mvp android-mvvm android-navigation android-navigation-graph android-navigationview android-ndk android-nested-fragment android-nestedscrollview android-networking android-night-mode android-notifications android-ondestroy android-optionsmenu android-orientation android-package-managers android-paging android-paging-3 android-pendingintent android-permissions android-phone-call android-popupwindow android-powermanager android-preferences android-productflavors android-progressbar android-proguard android-push-notification android-r8 android-radiobutton android-recents android-recyclerview android-relativelayout android-remoteview android-resources android-room android-room-embedded android-room-relation android-runonuithread android-runtime android-safe-args android-savedstate android-screen android-scroll android-scrollview android-sdcard android-sdk-2.3 android-sdk-manager android-sdk-tools android-search android-security android-securityexception android-seekbar android-sensors android-service android-service-binding android-settings android-shape android-sharedpreferences android-sharing android-shortcut android-signing android-snackbar android-softkeyboard android-source android-spinner android-splashscreen android-sqlite android-statusbar android-storage android-studio android-studio-2.2 android-studio-2.3 android-studio-3.0 android-studio-3.1 android-studio-3.1.4 android-studio-3.2 android-studio-3.3 android-studio-3.4 android-studio-4.0 android-studio-4.1 android-studio-4.2 android-studio-arctic-fox android-studio-bumblebee android-studio-chipmunk android-studio-dolphin android-studio-import android-styles android-subscriptionmanager android-support-design android-support-library android-switch android-tabbed-activity android-tablayout android-tablelayout android-tabs android-testify android-testing android-textinputedittext android-textinputlayout android-textwatcher android-theme android-timepicker android-tiramisu android-toast android-togglebutton android-toolbar android-touch-event android-tv android-typeface android-uiautomator android-vectordrawable android-version android-vibration android-videoview android-view android-viewbinding android-viewgroup android-viewholder android-viewmodel android-viewpager android-viewpager2 android-vitals android-volley android-wear-2.0 android-wear-3.0 android-wear-complication android-webview android-widget android-wifi android-windowmanager android-wireless android-workmanager android-x86 android-xml android-youtube-api androiddesignsupport androidsvg androidx angular angular-fullstack angular-http angular-material angular-reactive-forms angular-routing angular-services angular-ui-router angular13 angular2-nativescript angular2-routing angular6 angular7 angular8 angularjs animation annotate annotation-processing annotation-processor annotations anonymous ansi ansi-colors ansi-escape ansible ansible-galaxy ansible-inventory ant ant-contrib antialiasing antivirus antlr antlr4 any anychart anylogic anypoint-studio aop apache apache-atlas apache-beam apache-calcite apache-camel apache-camel-3 apache-commons apache-commons-beanutils apache-commons-collection apache-commons-compress apache-commons-config apache-commons-csv apache-commons-fileupload apache-commons-httpclient apache-commons-io apache-commons-lang3 apache-commons-logging apache-commons-text apache-curator apache-dubbo apache-felix apache-flex apache-flink apache-fop apache-httpasyncclient apache-httpclient-4.x apache-httpclient-5.x apache-httpcomponents apache-kafka apache-kafka-connect apache-kafka-streams apache-karaf apache-karaf-feature apache-mina apache-nifi apache-poi apache-ranger apache-servicemix apache-spark apache-spark-mllib apache-spark-sql apache-sshd apache-storm apache-stringutils apache-tika apache-tiles apache-tomee apache-zookeeper api api-authorization api-design api-documentation api-gateway api-key api4jenkins apk apksigner apostrophe app-startup app-store app-store-connect app.yaml appcenter appcompatactivity appdynamics append appender appfuse appgallery-connect appicon appium appium-android appium-desktop appium-ios apple-m1 apple-sign-in apple-silicon applescript applet application-lifecycle application-name application-restart application-server application-settings application-shutdown application.properties application.xml applicationcontext applinks applitools applovin appwidgetprovider apr apt apt-get aptana aptana3 arabic arabic-support arangodb arch archetypes architecture architecture-fitness-functions archiva archive archos archunit arcore arduino argb args argumentcaptor arguments arm arm64 armadillo array-key-exists arraylist arrays arrow-kt artemiscloud artifact artifactnotfoundexception artifactory artifacts ascii asciidoc asciidoctor asp.net asp.net-core asp.net-mvc asp.net-mvc-3 asp.net-mvc-4 aspect aspectj aspectj-maven-plugin aspose aspose-cells aspose.pdf assembly assert assertion assertions assertj assertthat associations asterisk-java async-await asyncapi asynchronous asynchttpclient asyncresttemplate asynctaskloader atest atg atlassian-sourcetree atmosphere atom-editor atom-feed atomic atomicinteger attachment attributes audio audio-player audio-recording audio-streaming audioinputstream audiorecord audiotrack audit audit-tables auditing augmented-reality auth0 authentication authenticator authorization authorization-server auto-close auto-generate auto-increment auto-indent auto-update autocloseable autocommit autocomplete autocompletetextview autofill autoformatting automated-refactoring automated-tests automatic-ref-counting automation automation-testing automotive autonumber autosuggest autotest autotools autowired avd avd-manager average avro avro-tools awaitility awk aws-amplify aws-amplify-sdk-android aws-api-gateway aws-app-mesh aws-cdk aws-cli aws-cloud9 aws-code-deploy aws-codeartifact aws-codebuild aws-codecommit aws-codepipeline aws-credentials aws-device-farm aws-ecr aws-fargate aws-java-sdk aws-java-sdk-2.x aws-java-sdk-dynamodb aws-lambda aws-media-convert aws-msk aws-sdk aws-secrets-manager aws-sqs-fifo aws-step-functions aws-steps aws-sts aws-vpc-peering aws-xray awt awt-eventqueue awtrobot axios axis axis2 axon axon-framework azul-zulu azure azure-active-directory azure-aks azure-app-configuration azure-app-service-envrmnt azure-application-insights azure-artifacts azure-blob-storage azure-cli azure-container-apps azure-cosmosdb azure-cosmosdb-sqlapi azure-databricks azure-devops azure-devops-pipelines azure-devops-rest-api azure-devops-server azure-files azure-functions azure-java-sdk azure-keyvault azure-maps azure-node-sdk azure-pipelines azure-pipelines-tasks azure-pipelines-yaml azure-repos azure-sql-database azure-sql-server azure-storage azure-vm-scale-set azure-web-app-service azureservicebus babeljs back back-button back-stack backend background background-color background-image background-process background-service background-task background-thread backoffice backport backpressure backspace backtracking backup backwards-compatibility bad-request badass-runtime-plugin badge bag ballerina bamboo banking banner-ads banno-digital-toolkit bar-chart barcode base base-url base64 base64url basehttpserver baseline-profile basex bash bash-trap basic-authentication batch-file batch-insert batch-processing batik bazel bazel-rules bcbsn bcrypt bdd beacon bean-validation beancreationexception beanshell bearer-token beautifulsoup beeware benchmarking beyondcompare bezier bidirectional big-o bigdecimal biginteger billingclient bimap bin binary binary-data binary-repository binary-search binary-search-tree binary-tree bind binding bintray bioinformatics biometrics birt birt-deapi bit-manipulation bitbucket bitbucket-api bitbucket-pipelines bitbucket-server bitbucket-webhook bitly bitmap bitmap-fonts bitmapfactory bitrate bitrise bitwise-operators black-box-testing blackberry blackberry-jde blackduck blade blame blaze-persistence blazor blink blob blockhound blocking bloomberg bluecove bluej blueprint-osgi bluestacks bluetooth bluetooth-gatt bluetooth-lowenergy blur bmp bnd boofcv boolean boolean-expression boolean-logic boost boot bootclasspath bootloader bootstrap-4 bootstrap-5 bootstrapping border borderpane boto3 bottom-navigation-bar bottom-sheet bottombar bottomnavigationview bottomsheetdialogfragment bounce bouncycastle bounded-types bounded-wildcard bounds bower bower-install boxlayout bpmn brackets braintree branch branch-prediction branch.io brave breadth-first-search break breakpoints bridge brightness brms broadcast broadcastreceiver broadleaf-commerce broker browser browser-automation browser-history browser-plugin browserstack brute-force bson bsondocument bubble-sort bucket4j buffer bufferedimage bufferedreader build build-automation build-helper-maven-plugin build-pipeline build-process build-tools build-variant build.gradle build.xml buildconfig builder building-github-actions buildozer buildpack buildpath buildship bukkit bulkinsert bulkupdate bundle bungeecord business-process-management butterknife button buttonbar buttongroup byte byte-buddy byte-code-enhancement bytearray bytearrayinputstream bytearrayoutputstream bytebuffer bytecode byteman bytestream bzt c c# c++ c++11 c++17 c++builder c3p0 cab cache-control caching caffeine caffeine-cache cakebuild cakephp calabash calabash-android calculator calendar californium call call-hierarchy call-recording callable callback camel-cxf camel-ftp camel-jms camel-rest camel-spring-dsl camel-test camelcasing camera camunda can-bus cannot-find-symbol canonicalization canvas capacitor capacitor-plugin capitalization capture cardlayout cardview caret cargo cargo-maven2-plugin carousel carriage-return cart cas cascade cascading cascading-deletes case cassandra cassandra-2.1 cassandra-3.0 casting castor catalina catalina.out catalog categories cdi cdn cdo-emf cds celery cellinfo cellrenderer cellular-network center centos centos6 centos7 cert-manager certbot certificate cglib cgroups challenge-response changelistener changelog changeset channel char character character-encoding charat charsequence charset chart.js charts chat chatbot check-constraints checkbox checked-exceptions checkmarx checkpoint checkstyle checksum cherry-pick chess children chipmunk chm chrome-custom-tabs chromecast chromium-embedded chronicle chronicle-bytes chunks cicd circleci circleci-2.0 circleci-workflows circuit-breaker circular-dependency circular-reference cisco-axl citrus-framework city clang class class-constructors class-hierarchy classcastexception classification classloader classname classnotfound classnotfoundexception classpath clean-architecture clever-cloud click clickable clickablespan clickhouse client client-server clientcredential clip clipboard clipboard-interaction clipboardmanager clob clojure clone cloneable closures cloud cloud-foundry cloudant cloudbees cloudbuild.yaml cloudcaptain cloudera cloudera-cdh cloudhub cloudinary cloudrail clover clover-payment cluster-computing cmake cmd cni coap cobertura cockroachdb cocoa-touch cocos2d-x cocoscreator code-analysis code-completion code-conversion code-coverage code-duplication code-formatting code-generation code-hinting code-injection code-inspection code-navigation code-organization code-regions code-signing code-signing-certificate code-standards code-templates codeblocks codec codecov codegen codeigniter codenameone codeready coderunner codesign codesniffer coding-style coffeescript coil cold-start coldfusion colima collapse collections collectors collision-detection color-picker color-scheme colors columnheader com combinations combobox comet cometd comma commaide command command-line command-line-arguments command-line-interface command-prompt comments commit common-table-expression communication companion-object comparable comparator compare compareto comparison compatibility compilation compile-time-constant compile-time-weaving compiler-bug compiler-errors compiler-optimization compiler-warnings completable-future completion-stage complexity-theory compojure component-scan components composable composer-php composite composite-id composite-key composite-primary-key composition compression computer-science conan concatenation concurrency concurrenthashmap concurrentmodification concurrentmodificationexception conda condition-variable conditional conditional-breakpoint conditional-statements confidential config configmap configurable configuration configuration-as-code configuration-files configurationproperties configure conflict confluence confluent-platform confluent-schema-registry connect connection connection-leaks connection-pooling connection-string connection-timeout connectionexception connectivity connector console console-application console.log constant-expression constantfolding constants constraint-layout-chains constraintlayout-guideline constraints constraintviolationexception construction-toy constructor constructor-injection consul consumer contactless-smartcard contacts containers contains content-assist content-disposition content-encoding content-length content-negotiation content-security-policy content-type contextmenu contextpath contextroot contextual-action-bar continuous continuous-delivery continuous-deployment continuous-integration contour contract control-p5 controller controller-advice controller-factory controllers controls controlsfx convenience-methods conventions converter converters convex-hull cookiecutter cookies coordinate coordinates copy copy-paste copyright-display corba corda cordova cordova-plugin-proguard cordova-plugins core coroutine coroutinescope corretto cors cors-anywhere cortex-m cosmos-sdk couchbase couchdb count countdown countdowntimer counter counting coverage.py cp1252 cpanel cplex cppcheck cppunit cpu cpu-architecture cpu-cores cpu-usage cql cqrs crash crashlytics crashlytics-android create-react-app create-table createquery creation credentials criteria criteria-api criteriabuilder criteriaquery crittercism crnk cron cron-task crop cross-browser cross-compiling cross-join cross-origin-read-blocking cross-origin-resource-policy cross-platform crud crud-repository cryptocurrency cryptographic-hash-function cryptography csh csrf csrf-protection csrf-token css css-grid css-selectors csv csvreader csvwriter ctakes ctest ctp ctypes cucumber cucumber-java cucumber-junit cucumber-jvm cucumber-serenity cucumber-spring cuda curl curly-braces currency currency-formatting cursor curve-25519 custom-adapter custom-arrayadapter custom-authentication custom-component custom-error-pages custom-events custom-renderer custom-rom custom-tag custom-view customization customvalidator cve cve-2021-44228 cvs cxf cxf-codegen-plugin cxf-xjc-plugin cyber-ark cyclic-dependency cygwin cypher cypress cyrillic daemon dagger dagger-2 dagger-hilt dalvik dao darkmode dart dart-2 dart-isolates dart-null-safety data-access-layer data-binding data-class data-conversion data-distribution-service data-driven-tests data-importer data-jpa-test data-migration data-persistence data-processing data-sharing data-structures data-transfer-objects database database-administration database-connection database-connectivity database-deadlocks database-design database-driven database-locking database-migration database-performance database-schema database-sequence database-versioning database-view databricks databricks-connect datadog dataflow dataframe datagram datagrid datainputstream datamatrix datanucleus datapersistance datasource datastax datastax-astra datastax-enterprise-graph datastax-java-driver datastore datatables datatables-1.10 dataweave date date-comparison date-conversion date-difference date-format date-formatting date-parsing date-range datediff datepicker datepickerdialog datetime datetime-format datetime-parsing datetimeformatter db2 db2-luw db2-zos dbca dbcp dbeaver dbref dbunit dbvisualizer ddl ddms ddos dead-code dead-letter deadlock deb debezium debian debian-buster debounce debug-mode debugging decimal decimalformat declarative declarative-services decoding decompiler decompiling decomposition decorator deep-linking deeplearning4j deeplink default default-constructor default-method default-parameters default-value defaultlistmodel defaulttablemodel definition deflate degrees delay delayed-job delete-directory delete-file delimiter delphi delta delta-lake density-independent-pixel dependabot dependencies dependency-injection dependency-management dependency-properties dependency-resolution dependency-tree deployit deployment deployment-descriptor deployment-diagram deprecated deprecation-warning derby dereference deserialization design-patterns designer desktop desktop-application destroy destructor detachedcriteria detect detection detox dev-mode deveco-studio developer-tools development-environment device device-admin device-name device-owner device-policy-manager devops devops-services devserver dex dfc dhl diacritics dialect dialog dialogflow-es dialogfragment diamond-operator dice dictionary diff difference diffie-hellman digg digital-ocean digital-signature digits dimension direct-runner direction directory directory-structure directory-traversal directx disable disabled-control disabled-input discord discord-jda discovery discriminator disk dism dismiss dispatcher display dispose distance distinct distinct-values distortion distributed distributed-computing distributed-tracing distributed-transactions divide-and-conquer divider division django django-models django-permissions django-rest-framework django-views djl dl4j dll dltk dns do-while docker docker-build docker-buildkit docker-compose docker-daemon docker-desktop docker-for-windows docker-image docker-in-docker docker-machine docker-maven-plugin docker-multi-stage-build docker-registry docker-run docker-secrets docker-swarm docker-volume dockerfile dockerhub document document-root documentfile documentlistener documents-provider docusignapi docusigncompositetmplts docx4j dokka dolby dom dom-events dom4j domain-driven-design dotenv dotnet-httpclient double double-click double-click-advertising doubly-linked-list download download-manager downloadfile doxia dozer dpi drag drag-and-drop draw drawable drawbitmap drawerlayout drawing drawtext driver drone.io drools drools-flow drools-guvnor drop-down-menu dropbox dropdown dropshadow dropwizard dropzone.js dry dsl dspace dto dual-sim duplicates duration dwave dynamic dynamic-feature-module dynamic-mapping dynamic-programming dynamic-proxy dynamic-text dynamic-url dynamodb-queries dynatrace e-commerce e2e-testing e4 each eager eager-loading ear eas easymock easywsdl ebean ecdh echo ecj eclemma eclipse eclipse-2018-09 eclipse-2019-03 eclipse-2019-09 eclipse-2020-06 eclipse-2021-09 eclipse-202209 eclipse-3.2 eclipse-3.3 eclipse-3.4 eclipse-3.6 eclipse-cdt eclipse-classpath eclipse-dtp eclipse-emf eclipse-emf-ecore eclipse-formatter eclipse-indigo eclipse-jdt eclipse-jee eclipse-juno eclipse-kepler eclipse-luna eclipse-marketplace eclipse-mars eclipse-mdt eclipse-memory-analyzer eclipse-neon eclipse-oxygen eclipse-pde eclipse-pdt eclipse-photon eclipse-plugin eclipse-pmd eclipse-rcp eclipse-rse eclipse-scout eclipse-tracecompass eclipse-wtp eclipselink ecmascript-6 ecore edi editing editor edittextpreference effect efxclipse egit egl ehcache either ejb ejb-2.x ejb-3.0 ejbca el elastic-stack elasticsearch elasticsearch-7 elasticsearch-aggregation elasticsearch-client elasticsearch-high-level-restclient elasticsearch-java-api electron elf ellipse ellipsis ellipsize elliptic-curve elytron emacs email email-attachments email-ext email-publisher email-validation embed embeddable embedded embedded-cassandra embedded-database embedded-jetty embedded-kafka embedded-resource embedded-tomcat embedded-tomcat-7 embedded-tomcat-8 ember.js emf emm emmet emoji emoticons emulation emv encapsulation encode encoding encrypted-shared-preference encryption encryption-asymmetric end-of-life end-to-end endianness endpoint endpoints enterprise-architect enterprise-integration entities entity entity-framework entity-relationship entitygraph entitylisteners entitymanager entitymanagerfactory enumerate enumeration enums environment environment-variables eofexception eol epic epoch epoxy epoxy-modelview equality equals equals-operator equinox erasure erd erlang erlide error-handling error-logging errorcollector errorprone esapi esb escaping esp32 euiccmanager euro eval event-driven event-handling event-listener eventhandler events eventsource examplematcher excel exception exception-handling exceptionhandler exchange-server exe exe4j exec exec-maven-plugin executable executable-jar execution executor executorservice exists exit exit-code exoplayer exoplayer2.x expand expandablelistadapter expandablelistview expected-exception exploit explorer expo expo-av expo-camera exponent exponentiation export export-to-excel express expression expressionbuilder extended-choice-parameter extends extentreports external extjs extract extraction fabric fabric8 fabric8-maven-plugin face facebook facebook-access-token facebook-android-sdk facebook-audience-network facebook-graph-api facebook-login facebook-sdk-4.0 facebook-sharer facelets facet faceted-search factory factory-pattern fadein faktor-ips fallback fast-refresh fastagi fastboot fasterxml fastify fastlane fastlane-snapshot fatjar fault-tolerance favicon fbaudience fdroid fdt feature-file feature-flags federated-identity fedora fedora-25 feed feign fetch fetch-api ff4j ffimageloading ffmpeg ffmpeg-php fibonacci fiddler fido field file file-descriptor file-exists file-generation file-handling file-io file-link file-locking file-permissions file-read file-saver file-security file-storage file-upload file-uri file-writing filechooser fileinputstream filelock filenames filenet-content-engine filenet-cpe filenet-p8 filenotfoundexception fileobserver fileoutputstream filepath filepond filereader filesize filesystems filewriter filter filtering final finalize find findall findbugs findby findelement findviewbyid fingerprint firebase firebase-ab-testing firebase-admin firebase-analytics firebase-authentication firebase-cloud-messaging firebase-dynamic-links firebase-mlkit firebase-notifications firebase-performance firebase-realtime-database firebase-remote-config firebase-security firebase-storage firebaseui firebird firefox firemonkey firewall fisheye fiware-knowage flags flapdoodle-embed-mongo flash-builder flashlight flask flatpak flexmark flink-sql flink-streaming flipper floating-action-button floating-point flooding flow flowable flowpane fluent fluent-bit fluent-nhibernate fluentwait fluid flutter flutter-3.0 flutter-android flutter-bottomnavigation flutter-build flutter-dependencies flutter-doctor flutter-getx flutter-in-app-purchase flutter-layout flutter-listview flutter-local-notification flutter-macos-2.0.0-stable flutter-material flutter-method-channel flutter-pageview flutter-plugin flutter-release flutter-secure-storage flutter-showmodalbottomsheet flutter-slider flutter-test flutter-web flutter-widget flux flying-saucer flyway focus focusmanager folding font-awesome font-face font-rendering font-scaling font-size fontawesomefx fonts for-loop foreach foreground foreground-service foreign-keys forgot-password forkjoinpool form-data form-submit format format-string formatter formatting formclosing forms formsflow formsflow.ai formula fortify fortify-source fortran forward forwarding fractions fragment fragment-backstack fragment-lifecycle fragment-shader fragmentmanager fragmentpageradapter fragmentstateadapter fragmentstatepageradapter fragmenttransaction frame frame-rate frameworks free freeglut freemarker freeze french frida frontend frontend-maven-plugin ftp ftp-client ftps full-text-search fullscreen function function-definition functional-interface functional-java functional-programming functional-testing fusedlocationproviderapi future fuzzy-logic fvm fxgl fxml fxmlloader fxyz3d g++ g1gc gallery game-development gant garbage garbage-collection gateway gatling gatling-plugin gcc gcloud gcov gcovr gcs gdb geckoview gelf gemfire generated generated-code generator generics genetic-algorithm genexus genymotion geo geocoding geode geofencing geofire geojson geolocation geometry geopoints geoserver geospark geospatial geotools gephi gerrit gerrit-trigger gesture gesture-recognition gesturedetector gesturelistener gestures get get-mapping get-request getelementsbytagname getline getparameter getpixel getresource getter getter-setter gettext gherkin ghidra ghprb gif gimp gis git git-bash git-branch git-checkout git-clone git-commit git-config git-crypt git-diff-tree git-fetch git-flow git-gui git-lfs git-log git-pull git-push git-refspec git-remote git-submodules git-svn git-tag git-webhooks git-worktree gitea github github-actions github-api github-api-v3 github-app github-copilot github-desktop github-package-registry github-packages github-pages github-release github-webhook gitignore gitkraken gitlab gitlab-api gitlab-autodevops gitlab-ci gitlab-ci-runner gitlab-ci.yml gitops gitversion glad glance glance-appwidget glassfish glassfish-3 glassfish-4 glassfish-5 glassfish-6 glew glfw glob global global-variables globalplatform glowroot glsl gltf gluon gluon-desktop gluon-mobile gluonfx glut gmail gmail-api gmaven-plugin gmavenplus gmt gnome gnu gnupg go go-cd go-to-definition goclipse google-admob google-advertising-id google-analytics google-api google-api-client google-api-java-client google-api-services-jobs google-app-engine google-app-engine-deploy google-artifact-registry google-assist-api google-authentication google-bigquery google-calendar-api google-cast google-chrome google-chrome-devtools google-cloud-build google-cloud-composer google-cloud-dataflow google-cloud-dataproc google-cloud-datastore google-cloud-debugger google-cloud-endpoints google-cloud-endpoints-v2 google-cloud-firestore google-cloud-functions google-cloud-kms google-cloud-load-balancer google-cloud-logging google-cloud-memorystore google-cloud-messaging google-cloud-platform google-cloud-pubsub google-cloud-pubsub-emulator google-cloud-run google-cloud-scheduler google-cloud-sql google-cloud-storage google-console-developer google-container-registry google-custom-search google-developers-console google-drive-api google-fit google-fit-sdk google-geocoder google-java-format google-kubernetes-engine google-location-services google-maps google-maps-android-api-2 google-maps-api-2 google-maps-api-3 google-maps-markers google-maps-urls google-oauth google-pay google-photos-api google-places google-places-api google-play google-play-console google-play-developer-api google-play-games google-play-services google-plus google-plus-signin google-search google-search-api google-secret-manager google-sheets-api google-signin google-sso google-translate google-vision google-voice googleads-mobile-unity googlemock googletest gprs gps gpu graaljs graalpython graalvm graalvm-native-image gradient gradle gradle-daemon gradle-dependencies gradle-eclipse gradle-kotlin-dsl gradle-plugin gradle-release-plugin gradle-shadow-plugin gradle-wrapper gradle.properties gradlefx gradlew grafana grafana-loki grails grails-2.0 grails-3.1 grails-3.3 grails-controller grails-orm grails-plugin grammar grape graph graph-algorithm graph-databases graphframes graphical-programming graphics graphics2d graphicscontext graphiql graphite graphql graphql-exception graphql-java graphstream graphviz gravity grayscale greendao gremlin gremlin-java grep grid grid-layout gridbaglayout gridlayoutmanager gridpane gridpanel gridview gridview.builder grizzly groovy groovy-console groovy-eclipse groovy-grape groovyshell group-by grouping groupingby grovepi+ grpc grpc-java gruntjs gson gsp gssapi gtk guacamole guava gui-builder guice gulp gulp-protractor gwt gwt-platform gwtmockito gxp gxt gyroscope gzip gzipinputstream gzipoutputstream h.264 h2 h2-console h2db h2o hadoop hadoop-yarn hamcrest handlebars.js handler hangout hapijs haproxy hardware hardware-acceleration hardware-security-module harmonyos hash hashcode hashicorp-packer hashicorp-vault hashmap hashset hashtable hateoas having haxm hazelcast hazelcast-jet hbase hbase-client hbm hbm2ddl hbmxml hbox hce hci hcl head header headless headphones headset health-check health-monitoring heap heap-dump heap-memory heap-profiling hebrew height heightmap helidon helios helm-templates helm3 helmfile heredoc heremap-navigation heremaps heremaps-android-sdk hermit heroku heroku-cli heroku-postgres hessian hex hexagonal-architecture hibernate hibernate-4.x hibernate-5.x hibernate-6.x hibernate-annotations hibernate-cache hibernate-criteria hibernate-entitymanager hibernate-envers hibernate-filters hibernate-generic-dao hibernate-jpa hibernate-mapping hibernate-native-query hibernate-ogm hibernate-onetomany hibernate-reactive hibernate-search hibernate-search-6 hibernate-spatial hibernate-tools hibernate-types hibernate-validator hibernate.cfg.xml hibernate3 hibernateexception hidpi hierarchical hierarchy high-availability highcharts highlight hikaricp hilo hint hippocms histogram history hive hivemq homebrew homebrew-cask hook horizontal-scrolling host hosting hostname hosts hot-reload hotkeys hotspot hotswap hotswapagent hotwire-rails hover hprof hql href hsqldb hssfworkbook hstore hsts hsv html html-escape-characters html-input html-select html-to-pdf html4 html5-audio html5-canvas htmlcleaner htmlunit htmlunit-driver htmx http http-accept-header http-accept-language http-content-length http-delete http-error http-get http-headers http-live-streaming http-message-converter http-method http-options-method http-patch http-post http-proxy http-redirect http-request-parameters http-response-codes http-status-code-204 http-status-code-400 http-status-code-403 http-status-code-404 http-status-code-405 http-status-code-415 http-status-code-500 http-status-code-503 http2 http4s httpclient httpconnection httpcookie httpd.conf httprequest httpresponse https httpserver httpsession httpsurlconnection httpurlconnection huawei-developers huawei-map-kit huawei-mobile-services huawei-push-notification huawei-safety-detect hubot hudson hudson-plugins hugo-logging hybrid-mobile-app hybris hyperledger hyperlink hystrix ibatis ibm-cloud ibm-mobilefirst ibm-mq icalendar icecast icepdf icons icu icu4j idbcommand ide ide-customization idempotent identifier identifying-relationship identity identity-column idioms ids if-none-match if-statement iframe ignite iis ijkplayer il2cpp illegal-characters illegalaccessexception illegalargumentexception illegalmonitorstateexcep illegalstateexception image image-cropper image-gallery image-generation image-processing image-resizing image-scaling image-scanner image-uploading imagebutton imagefilter imageicon imageview imap imasdk imgui immutability immutables-library imperva implementation implements import importerror imu in-app-billing in-app-purchase in-app-subscription in-clause in-memory-cache in-memory-database include incompatibility increment incremental-build indefinite indentation indexing indexof indexoutofboundsexception indy10 inet inetaddress infinispan infinite infinite-loop infinite-recursion inflate influxdb information-hiding informix inheritance init init-parameters initial-context initialization initrd inject inner-classes inno-setup input inputmismatchexception inputstream insert insert-id insomnia inspect instagram install4j installation installation-package instance instance-variables instanceof instant instant-run instantiation instructions instrumentation int integer integer-division integer-overflow integration integration-testing integrity intellij-13 intellij-14 intellij-15 intellij-idea intellij-idea-2018 intellij-idea-2020 intellij-inspections intellij-lombok-plugin intellij-plugin intentfilter intentservice interaction interceptor interface intern internal-server-error internal-storage internals internationalization internet-connection internet-explorer internet-radio interop interpolation interpreter interrupted-exception intersection interstitial introspection intuit invalid-characters invalidation invariance inversion-of-control invisible invisible-recaptcha invocationtargetexception invoke-command invokedynamic io ioc-container ioexception ionic-framework ionic-react ionic-v1 ionic-vue ionic2 ionic3 ionic4 ios ios-provisioning ios-ui-automation iostream iot ip ip-address ipfs iphone ireport is-empty ischecked isnullorempty isnumeric iso iso-8859-1 iso8583 isolation isolation-level isset istanbul istio itemizedoverlay itemprocessor itemtouchhelper itemwriter iterable iteration iterator itext itext7 iup ivy ivyde j8583 jaas jackson jackson-databind jackson-dataformat-avro jackson-dataformat-csv jackson-dataformat-xml jackson-modules jackson2 jacob jacoco jacoco-maven-plugin jacoco-plugin jadclipse jaeger jagged-arrays jakarta-ee jakarta-mail jakarta-mvc jakarta-servlet jandex janusgraph jar jar-signing jar-with-dependencies jarsigner jasmine jasmine-reporters jasper-reports jasperserver jaspersoft-studio jasypt java java-10 java-11 java-12 java-13 java-14 java-15 java-16 java-17 java-19 java-2d java-5 java-6 java-7 java-8 java-9 java-annotations java-batch java-bytecode-asm java-compiler-api java-ee-6 java-ee-7 java-ee-8 java-home java-http-client java-io java-me java-memory-leaks java-memory-model java-mission-control java-module java-native-interface java-nio java-package java-persistence-api java-platform-module-system java-record java-scripting-engine java-sealed-type java-security java-security-manager java-server java-stored-procedures java-stream java-threads java-time java-web-start java-websocket java-ws java.lang.class java.library.path java.nio.file java.time.instant java.util.concurrent java.util.date java.util.logging java.util.scanner javaagents javabeans javac javacard javacc javacompiler javadb javadoc javafx javafx-11 javafx-17 javafx-18 javafx-2 javafx-3d javafx-8 javafx-9 javafx-bindings javafx-css javafx-datepicker javafx-gradle-plugin javafx-tableview javafx-webengine javafx-webview javafxports javalin javapackager javaparser javaquery javascript javasound javassist javax-inject javax-measure javax-validation javax.crypto javax.imageio javax.json javax.persistence javax.validation javax.xml jave jax-rpc jax-rs jax-ws jaxb jaxb-episode jaxb2 jaxb2-basics jaxb2-maven-plugin jaxp jaxws-maven-plugin jaybird jbake jbcrypt jbehave jboss jboss-arquillian jboss-developer-studio jboss-eap-7 jboss-forge jboss-rules jboss-tools jboss5.x jboss6.x jboss7.x jbpm jbutton jcache jcasc jce jcenter jcheckbox jcodec jcombobox jconnect jconsole jcr jd-eclipse jdatechooser jdbc jdbc-pool jdbcnamedparametertemplate jdbcrealm jdbctemplate jdbi jdeps jdesktoppane jdeveloper jdic jdk-desugaring jdk1.5 jdk1.6 jdk1.7 jdk6 jdl jdo jdwp jedis jeditorpane jekyll jelly jemalloc jena jenkins jenkins-2 jenkins-api jenkins-blueocean jenkins-cli jenkins-declarative-pipeline jenkins-docker jenkins-email-ext jenkins-generic-webhook-trigger jenkins-git-plugin jenkins-github-plugin jenkins-groovy jenkins-jira-trigger jenkins-job-builder jenkins-job-dsl jenkins-kubernetes jenkins-pipeline jenkins-plugins jenkins-scriptler jenkins-shared-libraries jenkins-slack-plugins jenkins-slave jenkins-template-engine jenkins-update jenkins-workflow jenkins-x jenkinsfile jenv jep jersey jersey-2.0 jersey-3.0 jersey-client jersey-test-framework jestjs jetbrains-ide jetpack jetpack-compose-accompanist jetpack-compose-animation jetpack-compose-column jetpack-compose-navigation jetty jetty-10 jetty-8 jetty-9 jface jfilechooser jfoenix jform jform-designer jformattedtextfield jfr jframe jfreechart jfreechart-fx jfrog jfrog-xray jfuzzylogic jfxpanel jfxtras jgit jgiven jgrapht jgrasp jgss jhipster jhipster-gateway jhipster-registry jib jib-maven-plugin jibx jinternalframe jira jira-plugin jira-rest-api jira-rest-java-api jira-xray jit jitpack jitsi jitsi-meet jjwt jks jlabel jlink jlist jls jmc jmespath jmeter jmeter-5.0 jmeter-maven-plugin jmeter-plugins jmh jmock jmockit jmod jms jmstemplate jmstoolbox jmx jna jnativehook jndi jnlp job-scheduling jobrunr jobs jobservice jodatime jogl join joincolumn joinfaces jointable jolt jooq jooq-codegen-maven jopendocument jpa jpa-2.0 jpa-2.1 jpa-2.2 jpa-annotations jpa-criteria jpackage jpamodelgen jpanel jparepository jpasswordfield jpda jpeg jpos jpql jprofiler jprogressbar jq jqgrid jquery jquery-animate jquery-file-upload jqwik jradiobutton jrebel jrepl jruby jrubyfx jsch jscrollpane jsdoc jsessionid jsf jsf-2 jsf-2.2 jsf-2.3 jshell jshint jslint jsmooth jsobject json json-api json-deserialization json-patch json-schema-validator json-simple json-view json.net jsonb jsonexception jsonnode jsonobject jsonparser jsonpath jsonschema jsonserializer jsonslurper jsoup jsp jsp-fragments jsp-tags jspinclude jspinner jspx jsr jsr-275 jsr223 jsr286 jsr296 jsr310 jsr311 jsr330 jsr352 jsr356 jsr363 jsr380 jst jstack jstat jstl jta jtabbedpane jtable jtableheader jtds jtextarea jtextfield jtextpane jtree jts jukito jul-to-slf4j junit junit-jupiter junit-rule junit-runner junit3 junit4 junit5 junit5-extension-model junitparams jupyter-notebook justify jvi jvisualvm jvm jvm-arguments jvm-bytecode jvm-hotspot jwk jwt jwt-auth jxbrowser jxl jxloginpane jxls jython jzlib k0s kafka-consumer-api kafka-producer-api kaniko kanji kapt karaf karate karma-jasmine karma-runner katalon katalon-studio kattis keep-alive kendo-grid kendo-ui kerberos kettle key key-bindings key-value keyboard keyboard-events keyboard-navigation keyboard-shortcuts keychain keycloak keycloak-gatekeeper keycloak-rest-api keycloak-services keycode keyevent keyframe keylistener keymaps keystore keystroke keystrokes keytool keyword keyword-argument kibana kickstarter kie kill kill-process kitematic kivy kivymd kml knights-tour kodein kogito kohana-mangodb koin kong kotest kotlin kotlin-1.7 kotlin-android-extensions kotlin-coroutines kotlin-dokka kotlin-extension kotlin-flow kotlin-flow-flatmaplatest kotlin-interop kotlin-js kotlin-lateinit kotlin-maven-plugin kotlin-multiplatform kotlin-multiplatform-mobile kotlin-null-safety kotlin-reflect kotlin-sharedflow kotlin-stateflow kotlin-symbol-processing kotlin-when kotlin.notimplementederror kotlintest kotlinx kotlinx.coroutines ksoap2 ktlint ktor ktor-client kubeconfig kubectl kubernetes kubernetes-helm kubernetes-hpa kubernetes-ingress kubernetes-pod kubernetes-statefulset label lambda lambda-metafactory landscape landscape-portrait language-agnostic language-design language-server-protocol language-translation languagetool lanterna laravel large-file-upload last-modified lateinit latency latex latitude-longitude launch launch-configuration launch4j launchctl launchd launchdarkly launcher launching-application layer layout layout-editor layout-gravity layout-inflater layout-manager layout-xml layoutparams lazy-evaluation lazy-initialization lazy-loading lazycolumn ldap ldapauth ldif leading-zero leakcanary leanback legacy legend leiningen lenses less lets-encrypt lettuce libgdx libphonenumber libraries library-project libunwind libvlc licensing liclipse lifecycle lifecycleexception liferay liferay-6 liferay-7 liferay-7.3 lifo lightweight-stream-api limit line line-breaks line-count line-drawing line-numbers linear-gradients linear-search linearlayoutmanager linechart linefeed lines-of-code linkageerror linked-list linkedhashmap linker linker-errors linker-flags linkify linode lint linux linux-device-driver linux-kernel linux-mint liquibase liquibase-hibernate liquibase-maven-plugin liquibase-sql list listener listpreference listproperty listview listview-adapter listviewitem literate-programming live-streaming live-wallpaper llvm load load-balancing load-factor load-testing load-time-weaving loadimage loading local local-storage local-variables localdate localdatetime locale localhost localization localnotification localstack localtime location locationmanager locking locks lockscreen log4j log4j-1.2-cve log4j2 log4net logback logback-classic logcat logfactory logfiles logging logic logical-operators login logout logparser logstash logstash-logback-encoder lombok long-integer long-polling look-and-feel loops lottie lotus-notes low-latency ltree lts lua lucene lwjgl lwm2m lwuit lxml m2e m2eclipse m2m mac-address mac-app-store machine-learning machine-translation macos macos-big-sur macos-catalina macos-monterey macos-sierra macros magnetometer magnolia mail-sender mailgun main mainclass maintenance maintenance-mode makefile mamp managed-bean management.server.port manifest manifest.mf manjaro many-to-many many-to-one map mapbox mapbox-android mapbox-gl-js mapbox-marker mapbox-plugin mapmyindia-api mappedsuperclass mapper mapping mappingexception mapreduce maps mapstruct margin margins mariadb markdown marker markerclusterer markers marketplace marshalling maskformatter masking mass-assignment master-slave match matcher material-components material-components-android material-design material-dialog material-ui material-you material3 materialfx math matisse matlab matrix mattermost maui maui-blazor maui-community-toolkit maven maven-2 maven-3 maven-antrun-plugin maven-archetype maven-assembly-plugin maven-bom maven-bundle-plugin maven-cargo maven-central maven-checkstyle-plugin maven-clean-plugin maven-cobertura-plugin maven-compiler-plugin maven-dependency maven-dependency-check-plugin maven-dependency-plugin maven-deploy-plugin maven-ear-plugin maven-enforcer-plugin maven-exec-plugin maven-failsafe-plugin maven-flatten-plugin maven-frontend-plugin maven-gatling-plugin maven-gpg-plugin maven-indexer maven-install-plugin maven-invoker-plugin maven-jar-plugin maven-javadoc-plugin maven-jaxb2-plugin maven-jdeps-plugin maven-jetty-plugin maven-jib maven-jibx maven-lifecycle maven-metadata maven-mirroring maven-module maven-mojo maven-nar-plugin maven-package maven-plugin maven-profiles maven-publish maven-release-plugin maven-repository maven-resources-plugin maven-scm maven-settings maven-shade-plugin maven-site-plugin maven-source-plugin maven-surefire-plugin maven-toolchains maven-toolchains-plugin maven-versions-plugin maven-wagon-plugin maven-war-plugin maven-wrapper max maximize maximize-window maxlength maze md5 mdc mdm media media-player media-type mediabrowserservicecompat mediacontroller mediainfo mediametadataretriever mediamuxer mediapipe mediarecorder mediastore mediator mediaview memory memory-barriers memory-leaks memory-management menu menubar menuitem mercurial merge mergesort mesh message message-queue messagebox messagebroker messageformat messaging meta-inf meta-predicate metadata metamodel method-call method-interception method-invocation method-reference methodhandle methods metrics metro-bundler micro-optimization microbenchmark microk8s micrometer micronaut micronaut-client micronaut-data micronaut-gorm micronaut-security microphone microprofile microservices microsoft-edge microsoft-graph-api microsoft-graph-sdks microsoft-teams mifare miglayout migration milo mime mime-message mime-types min minecraft minecraft-fabric minecraft-forge mingw mingw32 minikube minimum minio miracast mismatch miui mixed mixins mkdirs mms mobfox mobile mobile-ad-mediation mobile-browser mobile-chrome mobile-development mobile-safari mobile-security mobile-website mocha.js mocking mockito mockito-inline mockk mockk-verify mockmvc mockrunner mockserver mockwebserver mod-cluster model model-binding model-view model-view-controller modelandview modelattribute modelmapper modifier modular modularity module module-info module-path mojarra mojibake mojo momentjs money-format mongo-java mongo-java-driver mongock mongodb mongodb-atlas mongodb-java mongodb-query mongorepository mongotemplate monitor monitoring monkey mono monocle monolithic monorepo monospace morphia moshi mosquitto motionevent motorola mount mouse-cursor mouseclick-event mouseevent mouselistener moxy mp3 mp4 mpandroidchart mpi mq mqtt ms-access ms-office ms-word msal msbuild mssql-jdbc msys2 msysgit mtom mtp mule mule-esb mule-studio mule4 mulesoft multi-database multi-database-connections multi-module multi-project multi-release-jar multi-select multi-tenant multi-touch multi-user multiautocompletetextview multibranch-pipeline multicast multichoiceitems multidimensional-array multifile-uploader multiline multilingual multimap multipart multipartfile multipartform-data multipath multiplayer multiple-accounts multiple-conditions multiple-databases multiple-monitors multiple-projects multiple-schema multiple-versions multiplexing multiplication multiprocessing multistage multithreading mustache mutable mutablelist mutablelivedata mutablemap mutation-testing mutiny mutual-authentication mv mvn-repo mvp mvvm mybatis mybatis-mapper myeclipse myfaces myget mylyn mysql mysql-5.7 mysql-8.0 mysql-connector mysql-workbench mysqlupgrade nakama named-parameters named-query namespaces naming naming-conventions naming-strategy nan nanohttpd nao-robot nashorn native native-methods nativequery nativescript nativescript-angular nativescript-vue nats.io nattable natural-key natural-sort naturalid navbar navigation navigation-architecture navigation-compose navigation-drawer navigationbar navigationcontroller navigationview navigator nd4j ndef ndk-build nebula negotiate neo4j neovim nested nested-class nested-exceptions nested-lists nested-loops nestedrecyclerview nestjs nestjs-swagger netbeans netbeans-10 netbeans-11 netbeans-12 netbeans-13 netbeans-14 netbeans-15 netbeans-6.9 netbeans-7 netbeans-7.1 netbeans-7.2 netbeans-7.3 netbeans-7.4 netbeans-8 netbeans-8.1 netbeans-8.2 netbeans-9 netbeans-platform netbeans-plugins netbeans6.5 netbeans6.7 netbeans6.8 netcdf4 netflix netflix-dgs netflix-eureka netflix-feign netflix-ribbon netflix-zuul netsuite netty netweaver network-programming network-security networking neural-network new-operator newline newman newrelic next-auth next.js nextflow nexus nexus-7 nexus3 nfc nfc-p2p ng-file-upload ng2-bootstrap nginx nginx-ingress nginx-reverse-proxy nhibernate nhibernate-mapping nhibernate-search nic nightly-build nimbus nimbus-jose-jwt nine-patch ninja nio nio2 nlog nlp noclassdeffounderror node-forge node-gyp node-http-proxy node-modules node-sass node.js node.js-typeorm nodeclipse nodes nohup non-alphanumeric non-ascii-characters non-nullable non-repeatable-read non-static nosql nosuchelementexception nosuchmethoderror not-exists notarize notepad++ notification-channel notificationmanager notifications notifydatasetchanged notin notnull npm npm-install nrf51 nrwl-nx nsdictionary nstableviewcell ntlm nuget null null-check nullability nullable nullpointerexception number-formatting numberformatexception numberpicker numbers numeric nunit nunit-3.0 nutch nvarchar nvidia nxp-microcontroller nxt oauth oauth-2.0 oauth-provider oauth2-server oauth2client oauth2resourceserver oauth2resttemplate obfuscation object objectaid objectanimator objectbox objectify objectinputstream objective-c objective-c++ objectmapper objectoutputstream observability observable observablecollection observablelist observer-pattern ocr ocsp odm odoo odoo-10 odroid office365 offline offset offsetdatetime ognl oh-my-zsh ojdbc okd okhttp okhttp3 okta oma omnet++ omnifaces omniorb onactivityresult onbackpressed onchange oncheckedchanged onclick onclicklistener onconfigurationchanged oncreate one-to-many one-to-one onedrive onesignal onhover onion-architecture onitemclicklistener onkeylistener onload onmouseclick onnx onpause onrestoreinstancestate onresume onsaveinstancestate ontouchlistener oom oomph oop opacity opc-ua opcode open-liberty open-session-in-view open-source open-telemetry openapi openapi-generator openapi-generator-maven-plugin opencl opencsv opencv opencv4android opendaylight openejb openfeign openfiledialog opengl opengl-es opengl-es-2.0 opengrok opengts openid openid-connect openide openjdk openjdk-11 openjdk-12 openjdk-17 openjdk-8 openjfx openjpa openjpa-maven-plugin openkm openldap opennlp openocd opensaml opensearch openshift openshift-3 openshift-client-tools openshift-pipelines openssh openssl openstreetmap opentype openvidu openwebbeans openwrt openxava operating-system operation operators oppo optaplanner optaweb-employee-rostering optgroup optimistic-locking optimization option option-type optional optional-parameters optionmenu options or-tools ora-00942 ora-12519 oracle oracle-apex oracle-aq oracle-enterprise-manager oracle-fusion-middleware oracle-jdk-17 oracle-jet oracle-objects oracle-ords oracle-sqldeveloper oracle-wallet oracle10g oracle11g oracle12c oracle18c oracle19c oracleforms oraclelinux orchestration order-of-execution ordereddictionary org.json organization orientation orm ormlite oscilloscope osgi osgi-bundle osgi-fragment osmdroid osx-mavericks osx-mountain-lion osx-yosemite ota out-of-memory outlook output output-window outputstream oval overlap overload-resolution overloading overriding overscroll owasp owl owl-api p2 p4a pa11y package package-info package-managers package-name package.json packages packaging packer packer-builder packet-capture packet-sniffers pact pact-broker pact-jvm padding page-factory page-lifecycle pageable pageobjects pagination paging paho paint paketo palette palindrome pandas pane panning papyrus parallel-builds parallel-execution parallel-processing parallel-testing parallels parallelstream parameter-passing parameter-splatting parameterization parameterized parameterized-tests parameterized-unit-test parameters parametrized-testing parcel parcelable parent parent-child parent-pom parentheses parse-platform parse-request parseexception parsing partition partitioning pass-data password-encryption password-protection passwords paste patch path path-finding path-parameter path-variables pattern-matching pause pax pax-exam payara payara-micro payload payment payment-gateway paypal paypal-sandbox paypal-webhooks paytm pbrun pcf pdb pdf pdf-conversion pdf-reader pdf-rendering pdf-viewer pdfa pdfbox pdfhtml pdi pear pecs peerjs pending-transition pentaho pepper percentage perf perfect-numbers perforce perforce-client-spec performance performance-testing perl permgen permission-denied permissions permutation persist persistence persistence.xml persistent personal-access-token perspective perspectivecamera perspectives pervasive pessimistic-locking petalinux pf4j pg-jdbc pgp phantomjs phase phoenix phone-call phone-number phonegap phonegap-build phonegap-plugins photo php php-7 php-7.4 php-8 php-cs-fixer phpdoc phpmyadmin phpstorm phpunit pi4j picard picasso picocli pie-chart pinchzoom ping pipe pipeline pipenv pitest pittesting pixel pixels pixmap pjsip pkce pkcs#11 pkcs#12 pkcs#7 pkcs#8 pkix plantuml platform play-billing-library playback playframework playframework-2.0 playn plexus plot plsql plugin.xml plugins pm2 pmd png pnpm podman point point-clouds pointcut pointers points pojo poker policy poller polling polygon polymer polymorphic-associations polymorphism pom.xml popup popupmenu popupmenubutton popupwindow port portable-applications porter-duff porting portlet portrait pos-tagger position post post-build post-processing post-processor postconstruct postgis postgresql postgresql-12 postgresql-13 postgresql-14 postgresql-9.1 postgresql-9.3 postgresql-9.4 postman postman-collection-runner postman-newman postman-testcase powermock powermockito powermockrunner powerpoint powerset powershell powershell-2.0 powershell-core pragma pre-commit-hook prebuild predestroy predicate preference preferenceactivity preferencefragmentcompat preferences preferencescreen prefix preflight preloader prepared-statement preserve pressed pretty-print preview preview-feature primary-key primavera primefaces primes primitive primitive-types principal printdialog printf printf-debugging printing println printstream printwriter priority-queue private private-key private-members private-methods private-repository privileges prng process processbuilder processing procfile procrun producer producer-consumer product production production-environment profile profiler profiling program-entry-point programmatically progress-bar progress-indicator progressdialog progressive-web-apps proguard proguard-maven-plugin project project-calico project-loom project-management project-panama project-reactor project-structure project-template projection projects projects-and-solutions prolog prolog-setof prometheus prometheus-pushgateway promise prompt propagation properties properties-file property-binding property-placeholder propertychangelistener propertychangesupport protected protege proto protobuf-c protobuf-java protoc protocol-buffers prototype prototype-scope protractor provisioning proxmox proxy proxy-classes proxy-protocol proxypass pscp pseudocode psexec psr-0 ptc-windchill ptv-developer pub.dev public public-key public-key-encryption publish publish-subscribe publishing pug pull-request pull-to-refresh pulsar pulumi purge push push-notification put putty pyarrow pycharm pydev pylint pyodbc pyomo pyspark pytest pytest-bdd python python-2.7 python-2to3 python-3.6 python-3.x python-appium python-behave python-import python-requests python-unittest python-venv python-xarray qa qaf qemu qml qpid qr-code qt qt-creator qt-vs-addin qtandroidextras qtest qtserialport quality-gate quantum-computing quarkus quarkus-panache quarkus-reactive quarkus-rest-client quartz quartz-scheduler quasar quaternions query-builder query-by-example query-optimization query-parameters query-string querydsl queryparam queue quickcheck quickfix quickfixj quicksort qunit quotation-marks quotes r r2dbc r2dbc-mysql rabbitmq rabbitmq-exchange race-condition rad radians radio-button radio-group radius radrails raku random random-seed range-query ranking raspberry-pi raspberry-pi-pico raspberry-pi-zero raspberry-pi2 raspberry-pi3 raspberry-pi4 rate rate-limiting rational-team-concert raw rc rcp rcpp rdbms rdd rdf4j react-admin react-hooks react-native react-native-android react-native-cli react-native-contacts react-native-flatlist react-native-fs react-native-maps react-native-navigation react-native-reanimated react-native-reanimated-v2 react-native-video react-native-web react-native-webview react-navigation react-navigation-stack react-navigation-v6 react-redux react-router react-table react-typescript reactive reactive-feign-client reactive-mongo-java reactive-programming reactive-streams reactjs reactor reactor-kafka reactor-netty reader readfile readme readonly realm realpath rebuild recaptcha recaptcha-v3 recognizer-intent record records recover recovery recreate rectangles recursion recursive-backtracking recyclerlistview redhat redirect redirect-uri redis redis-cache redis-cluster redis-sentinel redisson redmi-permission redoc reduce redundancy redux refactoring reference reference-library referer reflection reflections refresh regex regex-group regex-negation regexp-replace registerforactivityresult registration registry reindex relational-database relationship relative-locators relative-path release release-apk release-builds release-management reload remote-access remote-debugging remote-execution remote-repository remote-server remoteobject remoteview remotewebdriver remoting removing-whitespace rename render renderer rendering renderscript renovate repeat replace replication repo report reporting repository repository-pattern request request-headers request-mapping request-validation requestdispatcher requestfactory requestscope requirements.txt reserved-words reset-password resilience4j resilience4j-retry resize resolution resolve resource-leak resourcebundle resources response response-entity response-headers responsive-design rest rest-assured rest-assured-jsonpath rest-client restapi restart resteasy restful-architecture restful-authentication restful-url resthighlevelclient restlet restriction resttemplate resultset resume retain rethinkdb retina-display retrofit retrofit2 retrolambda retry-logic return return-type return-value revenuecat reverse reverse-engineering reverse-proxy review revision-history rfc3986 rfid rgb rhel ria richfaces richtextfx rider right-to-left rights ripple-effect rls rmi robocopy robolectric robot robotframework robotium robots.txt rocket.chat role role-base-authorization role-based roles rollback rollout rom roman-numerals roomdb root rosetta-2 rotation rounded-corners rounding routing row row-level-security rpc rpm rpm-maven-plugin rpmbuild rsa rsa-key-fingerprint rsocket rspec rsql rsrc rss rsync ruby ruby-on-rails rubygems rule rule-engine rules run-configuration runas rundeck rundll32 runnable runnable-jar runtime runtime-error runtime-permissions runtimeexception rust rvm rx-android rx-java rx-java2 rx-java3 rx-kotlin rxjs saaj sablecc saga samba saml saml-2.0 sampling samsung-galaxy sanitization sap sap-ase sap-commerce-cloud sap-fiori sapui5 saripaar sass saucelabs save savedstateviewmodelfactory saving-data sax saxparser sbt sca scala scala-2.7 scala-breeze scala-collections scala-gatling scala-java-interop scala-maven-plugin scala-metals scala-option scalability scalafx scalar scalatest scalatest-maven-plugin scale scaling scanf scanning scatter-plot scene scenebuilder schedule scheduled-tasks scheduledexecutorservice scheduler scheduling schema schemagen scikit-learn scjp scons scope scoped-storage scp screen screen-capture screen-orientation screen-readers screen-recording screen-resolution screen-rotation screen-scraping screenshot screenshot-testing script scriptengine scripting scriptlet scroll scrollable scrollbar scrollpane scrollview scylla sd-card sdcc sdk sdkman sdl-2 sealed-class seam seam2 search searchbar searchview second-level-cache secondary-table secret-key security securityexception securitymanager sed seekbar-thumb segger-jlink segmentation-fault select select-n-plus-1 selected selecteditem selection selection-sort selectionchanged selector selenide selenium selenium-chromedriver selenium-extent-report selenium-firefoxdriver selenium-grid selenium-iedriver selenium-jupiter selenium-webdriver selenium4 selenoid self-contained self-invoking-function self-signed semantic-ui semantic-versioning semantic-web semantics sencha-touch sencha-touch-2 send sendasync sendgrid sendmail sensors sentinel sentry seq sequelize-auto sequence sequence-generators sequences sequential sequential-workflow serenity-bdd serenity-js serial-port serializable serialization series server server-configuration server-sent-events server-side server-side-rendering server-side-validation server.xml serverless serverless-framework serversocket service service-accounts service-discovery service-layer service-virtualization service-worker servicebus serviceloader servlet-2.5 servlet-3.0 servlet-4 servlet-container servlet-dispatching servlet-filters servlet-listeners servlet-mapping servletconfig servletcontextlistener servletexception servlets session session-cookies session-fixation session-hijacking session-management session-scope session-state session-storage session-timeout session-variables sessionfactory sessionid set setcontentview setcookie setfocus setter settext settimeout settings sftp sh sha1 sha256 shader shadow shadow-dom shadowjar shallow-clone shape shapes sharding share share-intent shared shared-directory shared-libraries sharedpreferences sharepoint shedlock shell shibboleth shippo shiro shopping-cart short shortcut shortcuts shoutcast shrinkresources shrinkwrap shutdown shutdown-hook sicstus-prolog side-effects sidecar sigabrt sightly sign signal-processing signalr signalr-hub signals signature signed signed-apk signing sigterm sikuli sikuli-x sim-card simd simplecaptcha simplecursoradapter simpledateformat simplehttpserver simulation simulator simultaneous single-page-application single-sign-on single-table-inheritance singlechildscrollview singleton singly-linked-list sip sitemap sitemesh size skaffold skija skin skipper slack slack-api slave sleep slf4j slider slidingmenu sling smack smali smalltalk smartcard smartgwt smartphone smooth-scrolling sms sms-retriever-api smtp snackbar snakeyaml snapshot sni snowflake-cloud-data-platform snyk soap soap-client soapfault soapui socket.io socket.io-client socketexception sockets sockjs soft-delete soft-keyboard softhsm softmax software-quality solaris solid-principles solr solrj sonar-maven-plugin sonar-runner sonarcloud sonarlint sonarlint-eclipse sonarqube sonarqube-4.5 sonarqube-api sonarqube-ops sonarqube-scan sonarqube-web sonarqube5.1 sonarscanner sonatype sorted sortedmap sortedset sorting source-compatibility source-sets space spaces spannable spannablestring spannablestringbuilder spark-cassandra-connector spark-java spark-kafka-integration spark-streaming spark-structured-streaming spark3 sparql spatial specflow special-characters specifications speech-recognition speech-synthesis speech-to-text spell-checking spelling spigot spine spinnaker spinner spire.doc splash-screen split split-screen splitpane spnego spock spoon spotbugs spotify spotless spring spring-3 spring-4 spring-actuator spring-amqp spring-annotations spring-aop spring-aspects spring-async spring-autoconfiguration spring-batch spring-batch-admin spring-batch-job-monitoring spring-batch-stream spring-batch-tasklet spring-bean spring-boot spring-boot-2 spring-boot-2.6.0 spring-boot-3 spring-boot-actuator spring-boot-admin spring-boot-configuration spring-boot-devtools spring-boot-gradle-plugin spring-boot-jpa spring-boot-maven-plugin spring-boot-starter spring-boot-starter-parent spring-boot-test spring-cache spring-camel spring-cloud spring-cloud-aws spring-cloud-circuitbreaker spring-cloud-config spring-cloud-config-server spring-cloud-consul spring-cloud-contract spring-cloud-dataflow spring-cloud-feign spring-cloud-function spring-cloud-gateway spring-cloud-gcp spring-cloud-kubernetes spring-cloud-loadbalancer spring-cloud-netflix spring-cloud-sleuth spring-cloud-stream spring-cloud-stream-binder-kafka spring-cloud-vault-config spring-config spring-content-community-project spring-context spring-data spring-data-cassandra spring-data-couchbase spring-data-elasticsearch spring-data-gemfire spring-data-jdbc spring-data-jpa spring-data-jpa-datatables spring-data-mongodb spring-data-mongodb-reactive spring-data-neo4j spring-data-neo4j-4 spring-data-r2dbc spring-data-redis spring-data-redis-reactive spring-data-rest spring-dsl spring-el spring-filter spring-form spring-framework-beans spring-graphql spring-hateoas spring-initializr spring-integration spring-integration-amqp spring-integration-aws spring-integration-dsl spring-integration-http spring-integration-ip spring-integration-mqtt spring-integration-sftp spring-ioc spring-java-config spring-jdbc spring-jms spring-jmx spring-json spring-junit spring-kafka spring-kafka-test spring-ldap spring-logback spring-messaging spring-micrometer spring-mongo spring-mongodb spring-mvc spring-mvc-initbinders spring-mvc-test spring-mybatis spring-native spring-oauth2 spring-orm spring-portlet-mvc spring-profiles spring-projections spring-properties spring-rabbit spring-reactive spring-repositories spring-resource-server spring-rest spring-restcontroller spring-restdocs spring-resttemplate spring-retry spring-roo spring-saml spring-scheduled spring-security spring-security-acl spring-security-ldap spring-security-oauth2 spring-security-rest spring-security-saml2 spring-security-test spring-security4 spring-session spring-shell spring-starter spring-statemachine spring-test spring-test-dbunit spring-test-mvc spring-thymeleaf spring-tld spring-tool-suite spring-tools-4 spring-transactions spring-validation spring-validator spring-vault spring-web spring-webclient spring-webflow spring-webflux spring-websocket spring-ws spring5 springdoc springdoc-openapi-maven-plugin springdoc-openapi-ui springdoc-openui springdoc-ui springfox springfox-boot-starter springjunit4classrunner springmockito springrunner springsource sprint spy sql sql-delete sql-injection sql-insert sql-like sql-null sql-server sql-server-2005 sql-server-2012 sql-server-2014 sql-update sql-view sqlcipher-android sqlexception sqlite sqlite-net sqliteopenhelper sqlplus sqlresultsetmapping square squid squish ssdp ssh ssh-keys ssh-tunnel sshj sshpass ssl ssl-certificate sslcontext sslengine sslerrorhandler sslexception sslhandshakeexception sspi stack stack-memory stack-overflow stack-trace stackdriver stackexchange-api stackpanel stage standards stanford-nlp start-activity startup startup-error state state-machine state-management stateflow stateful stateless static static-analysis static-block static-code-analysis static-content static-factory static-import static-methods static-polymorphism static-resource static-variables staticresource statistics status statusbar stderr stdio stdout steganography stencil-buffer stig stm32 stomp stompjs storage storage-access-framework storage-file-share store stored-procedures stream streaming string string-comparison string-concatenation string-formatting string-interpolation string-length string-matching string-pool string-substitution stringbuffer stringbuilder stringindexoutofbounds strip stripe-payments stripes struct structural-search structure struts struts-1 struts-config struts-validation struts2 struts2-convention-plugin struts2-interceptors struts2-junit-plugin struts2-s2hibernate sts sts-springsourcetoolsuite stub stubbing styleddocument styles stylesheet styling subclass subclipse subdirectory subdomain sublimetext2 sublimetext3 submenu subquery subscript subscription subscriptions subsequence subset substring subtitle subtraction subversive sudo sudoku suitecloud suitescript sum sumo sun sunpkcs11 super superclass supercsv superglobals superscript supplier supportmapfragment suppress suppress-warnings surefire surfaceview suspend sutime svg svg-android svg-path svn svnkit swagger swagger-2.0 swagger-3.0 swagger-codegen swagger-ui swap swift swig swing swingbuilder swingutilities swingworker swingx swipe swiperefreshlayout swipeview switch-statement swt swtbot sybase symbols symfony symfony4 symlink syncfusion synchronization synchronized synchronized-block syntax syntax-error syntax-highlighting sys-refcursor sysdate sysfs system system-design system-properties system-variable system-verilog system.out systemc systemctl systemd systrace table-per-class tablecell tablecellrenderer tablecolumn tablelayout tablemodel tablerowsorter tablesaw tablet tableview tableviewer tabpanel tabs tagging taglib tags tailwind-css talend talkback tamil tapestry tar target target-platform targetsdkversion task taskbar taskkill taurus tcp tcpdump tcserver tcsh tdd team-explorer-everywhere teamcity tekton tekton-pipelines telegraf-output-plugins telegram telegram-bot telephony telephonymanager television temp-tables template-engine templates temporary-directory temporary-files tensorflow tensorflow-lite tensorflow2.0 teradata terminal terminate terminology termux terraform terraform-provider-aws terraform-provider-gcp tess-two tess4j tesseract test-coverage test-reporting test-runner test-suite testability testcafe testcase testcontainers testcontainers-junit5 testfx testing testng testng-dataprovider testng-eclipse testng.xml text text-alignment text-cursor text-editor text-extraction text-files text-manipulation text-size text-to-speech textarea textbox textcolor textfield textflow textinputlayout textselection textstyle texture-mapping textview textwatcher textwrangler tflite tfs thawte theia themes theory this thread-confinement thread-local thread-safety thread-sleep threadpool threadpoolexecutor three.js thrift throw thumbnails thymeleaf tibco-ems tic-tac-toe ticker tidy tiff tiles tiles2 time time-complexity time-format time-precision time-series timedelta timeline timeout timeoutexception timepicker timer timertask timestamp timestamper timezone timsort tinder tinkerpop tinkerpop3 tinylog tinymce tinymce-plugins title tls1.2 tls1.3 tmx tns tnsnames toast todo toggle togglebutton token tokenize tomcat tomcat-jdbc tomcat-manager tomcat-valve tomcat10 tomcat5.5 tomcat6 tomcat7 tomcat8 tomcat8.5 tomcat9 tomee-7 tomee-8 toolbar toolchain tools.jar tooltip tor tornadofx tortoisesvn tostring touch touchpad trace traffic trailing-slash training-data traits transactional transactionmanager transactions transformation transient transition transitions transitive-dependency translate-animation transparency transparent traversal travis-ci tree treemap treeset treetable treetableview treeview trial triangulation triggers trigonometry trim truestudio truezip truncation trusted-timestamp truststore try-catch try-catch-finally try-with-resources ttl turbine turbo turtle-rdf twilio twilio-api twitter twitter-bootstrap twitter-bootstrap-3 twitter-bootstrap-4 twitter4j two-way-binding twos-complement txt tycho tycho-surefire-plugin type-alias type-conversion type-erasure type-inference type-mismatch typeface typeorm types typesafe-config typesafe-stack typescript typing typo3 typo3-6.2.x uac ubuntu ubuntu-10.04 ubuntu-12.04 ubuntu-14.04 ubuntu-16.04 ubuntu-17.04 ubuntu-18.04 ubuntu-20.04 ubuntu-22.04 ucanaccess ucp udp ui-automation ui-testing ui-thread uicolor uilocalnotification uinavigationbar uirepeat uitest uiviewcontroller uml unary-operator unauthorized unc uncaught-exception uncaughtexceptionhandler undefined underline undertow undo undo-redo unhandled-exception unicode unicode-escapes uninstallation unique unique-constraint unique-id unirest unit-of-work unit-testing units-of-measurement unity3d unix unix-timestamp unknown-host unmarshalling unmodifiable unpack unsafe unsatisfiedlinkerror unsigned unsigned-integer unsupported-class-version unsupportedoperation unused-functions unused-variables unzip update-site updates updating upgrade upload uppaal upstart uri uribuilder url url-mapping url-parameters url-pattern url-redirection url-rewriting url-routing url-validation urlclassloader urlconnection urldecode urlencode urlstream usage-statistics usb usb-debugging use-state user-agent user-defined user-defined-types user-input user-interface user-management user-permissions userdetailsservice userprincipal ussd utc utf utf-8 utilities uuid uv-mapping uvm vaadin vaadin-flow vaadin-grid vaadin14 vaadin21 vaadin22 vaadin23 vaadin7 vaadin8 vagrant valgrind validation valuestack var varchar variables variadic-functions vault vb.net vb6 vba vbox vcf-vcard vector velocity veracode vercel verify verifyerror verilog version version-compatibility version-control version-numbering versioning versions versions-maven-plugin vert.x vertex vertex-shader vertica vertx-eventbus vertx-verticle vertx4 vfs viber vibration video video-capture video-player video-processing video-streaming view viewaction viewgroup viewmodel viewmodelfactory viewmodelproviders viewport viewroot views viewstub vim virtual-functions virtual-machine virtual-reality virtualbox virtualenv virtualization virtuoso visibility visible visual-studio visual-studio-2010 visual-studio-2013 visual-studio-2022 visual-studio-app-center visual-studio-code visualsvn-server visualvm vitess vlc vlc-android vlcj vmargs vmware voice voice-recognition void voip volatile vosk vowpalwabbit vpn vps vscode-code-runner vscode-settings vsphere vtd-xml vue-cli vue-resource vue.js vuejs2 wadl wagon wait wakelock wakeup wallpaper wamp war war-filedeployment warnings warnings-next-generation was watch watchface wav wcf weak-references weakhashmap wear-os wear-os-tiles web web-api-testing web-application-design web-applications web-audio-api web-config web-container web-content web-deployment web-development-server web-fragment web-frameworks web-hosting web-inf web-project web-scraping web-services web.xml web3-java webauthn webautomation webclient webcontext webdriver webdriver-io webdriver-manager webdriver-w3c-spec webdrivermanager-java webdriverwait webfiltering webflux webgl webgoat webhooks webjars webkit weblogic weblogic-10.x weblogic11g weblogic12c webp webpack webrtc websecurity webserver webservice-client websocket websphere websphere-8 websphere-liberty websphere-portal webstorm webtestclient webui webview webviewchromium webviewclient weka welcome-file weld wget whatsapp while-loop white-labelling whitesource whitespace wicket widget width wifi wifi-direct wifimanager wikitude wikitude-sdk wildcard wildcard-mapping wildfly wildfly-10 wildfly-15 wildfly-18 wildfly-26 wildfly-8 wildfly-9 wildfly-swarm wildwebdeveloper window window-handles window-soft-input-mode windowbuilder windows windows-10 windows-11 windows-7-x64 windows-defender windows-installer windows-phone-8 windows-security windows-server-2012-r2 windows-server-2016 windows-services windows-subsystem-for-linux windows-task-scheduler windows-virtual-pc windows-vista windowsbuilder winget winmain winrm winscp winsock2 winston winstone wiremock wiremock-standalone wireshark wix3.5 wizard wkt word-count word-wrap wordpress work-stealing worker workflow working-directory working-set workmanagers workspace wpf wrapper ws wsdl wsdl2java wsimport wsl-2 wso2 wso2-esb wso2ei wso2esb x-forwarded-for x-frame-options x-www-form-urlencoded x11 x509 x509certificate x86 x86-64 xalan xamarin xamarin-studio xamarin.android xamarin.forms xamarin.uitest xaml xampp xcode xcode-plugin xcodebuild xcopy xctest xcuitest xdebug xdocreport xerces xhtml xiaomi xilinx-edk xjc xl-deploy xlm xlsx xml xml-attribute xml-binding xml-configuration xml-editor xml-parsing xml-rpc xml-validation xmlbeans xmlbeans-maven-plugin xmlencoder xmlgregoriancalendar xmlhttprequest xmlslurper xmlunit xmlworker xmpp xodus xor xpages xpath xquery xsbt-web-plugin xsd xsd-validation xslt xss xssf xstream xtend xtext xunit.net xvfb yakode yaml yarn-v2 yarnpkg yawl yearmonth yelp yelp-fusion-api yguard yii yocto youtrack youtube youtube-api youtube-data-api youtube-dl youtubeplayer yubico yubikey yui yui-compressor yum z-order zalo zap zend-studio zero zeromq zerossl zgc zip zip4j zipfile zipinputstream zipkin zipoutputstream zk zlib zoneddatetime zooming zsh zxing zxing.net

Copyright © JavaFixing